Construction Updates - Week Ending October 8, 2021
La Grange Road/31st Street Water Main Replacement: This week, Lindahl dug out the western half of the north alley and prepared the new sub-base for the concrete sub-contractor to frame and pour the new surface. Unfortunately, this week's rain hampered progress. The sub-contractor began removing the old sidewalks on La Grange Road, south of the BP station. Today they will complete the removals and begin framing for the new sidewalks. We hope the rain holds off next week to get the sidewalks and alley poured with fresh cement.
Meadowcrest Road/Woodside Avenue Repaving Project: Lindahl's sub-contractor began removing and replacing the curbs and aprons on the west sides of Meadowcrest Road and Woodside Avenue. Progress was slightly delayed this week due to the rain. The contractor is framing and pouring concrete today and expects to finish next week.
Nicor Gas Project (IHB to Kemman Avenue, between 31st Street & Oak Avenue):
Work completed to date (10/4 – 10/8)
- Saw cut and removal of all sidewalk over existing utilities on Beach between Monroe and 31st Street
- Excavation on Jackson near Kemman for directional drill of 2" gas pipe
- Directional drill on Newberry from Garfield near 31st Street
- Directional drill on Jackson between Newberry and Kemman
- Spot utilities on Beach between Monroe and 31st Street
- Directional drill on Beach between Monroe and 31st Street
- Core road to spot and utilities being crossed in these locations
- Saw cut and removal of sidewalk over existing utilities on Newberry between Harding and Oak
- Saw cut and removal of sidewalk over existing utilities on Beach between Harding and Oak
- Directional drill on Newberry between Harding and Oak
- Saw cut and removal of sidewalk over existing utilities on Oak between Newberry and Kemman
- Backfill on Newberry between Harding and Oak
- Excavation on SE corner of Harding and Beach to connect gas mains
Upcoming work schedule (10/11 – 10/16)
- Backfill of excavation on SE corner of Beach and Harding
- Backfill on Beach and Newberry between Harding and 31st Street
- Saw cut and remove sidewalk over existing utilities on Kemman between Harding and 31st Street
- Hand locate or vacuum truck all utilities to be crossed
- Saw cut and remove sidewalk over existing utilities on Beach from Harding to Oak
- Core road to spot and utilities being crossed in these locations
- Directional drill gas pipe on Beach between Harding and Oak
- Saw cut and remove sidewalk over existing utilities on Kemman between Harding and 31st Street
- Locate any existing utilities on Kemman between Harding and 31st Street
- Excavation on Beach between Harding and Oak for directional drill
- Excavation on Oak for directional drill