Construction Updates - Week Ending August 6, 2021
La Grange Road/31st Street Water Main Replacement:
Suburban General dug a few pits this week to take soil samples around the service station to determine soil conditions before the project begins. The start date is pushed back to the week of August 16th, with the contractor starting on the northern phase of the project. Check back next week for more details.
31st Street Bridge over the Salt Creek Repairs: No update this week.