Construction Updates - Week Ending April 23, 2021
Sewer Point Repair: Suburban General completed the last repair and began restorations this week. Next week, the contractor hopes to finish all the restorations for this project.
Ogden Ave. Resurfacing (IDOT Project): The Village of La Grange Park was not notified by IDOT that Ogden Avenue, between Edgewood Avenue and I-294, was slated for resurfacing this year. Construction commenced this week and will continue for the next 35 working days. IDOT's contractor has begun saw cutting the intersections and sidewalks at the corners. Next week, the sidewalks in the radius of the intersections will be removed and replaced with new concrete and ADA tiles.
Maple Ave./17th Ave. Resurfacing (IDOT Project): This week, the crosswalks and spot curb replacements on the La Grange Park side of Maple Avenue, between 26th Street and 31st Street, were removed and are ready for concrete next week.