Updates will be made as they become available:
Construction Updates - Week Ending October 14, 2022
Nicor Gas Project (West of IHB to La Grange Road, between Homestead and Garfield: Nicor’s restoration contractor is progressing greatly with replacing concrete sidewalks and making landscape restorations. This work will continue for the next few weeks until the project is complete.
26th Street Road Paving Project:
M&J completed installing the asphalt binder course, and their subcontractor adjusted all manholes in the paving limits. Landscape restoration began this week also. The goal is to concrete around the frame adjustments on Monday, which may need a few days to cure. After which the asphalt surface material will be put down by the end of the week. Check back next week for the last update on this project.