Construction Updates - Week Ending April 15, 2022
Permeable Pavement/Green Infrastructure Intersections: Copenhaver made great progress this week. Their subcontractor completed the brick installation at the Community/Monroe intersection, and the intersection is now open for vehicle traffic. Next week, Copenhaver will begin to prepare for landscaping at this location. The Sherwood/Monroe intersection work continues to progress nicely as well. The water main installation is complete, the underdrain system is installed, and backfilling is complete. Next week, the concrete curbs and ribbon will get installed and the sub-contractor will install the bricks. This intersection is expected to open by the end of next week.
Sewer Point Repair Project: Unique Plumbing completed the work on Spring this week, but the remaining work will be completed next week due to the rain event. Once the work on Stone is complete, the contractor will repair the concrete pavement on both blocks simultaneously.