News Flash

Home

Posted on: April 3, 2019

Weekly Construction Updates

Construction Zone

Updates will be made as they become available:

Construction Updates - Week Ending September 13, 2019 

For a comprehensive list of updates, please click here. 

  • Sunnyside Sanitary Project Update: Noticeable progress was achieved by the contractor this week. Vacuum testing of the new sewer from the west bank of the creek to 31st St is underway.   Asphalt removal, topsoil installation and grading of the bike path from the creek heading west has begun this week. The temporary drainage pipe was removed along the east side of Edgewood. The clearing of debris and material has continued at the bus turn around location. The contractor is on schedule to install the new asphalt for the bike path and Edgewood before the September 30th deadline.
        
  • Raymond Water Main Replacement Update: Now that the new water main underground work is complete, the remaining work is to begin restorations. The contractor needs one more week for the trenches to settle before the concrete work begins. Next week, framing and pouring concrete, sidewalks, curbs, aprons and repairs to damaged areas will be underway. Please be advised that if you live in this area, your driveway access will be limited once pouring of the concrete begins. Check back next week for another update.  
      
  • La Grange Road and 31st Water Main Replacement Update: At Tuesday night’s Board Meeting, a new agreement was entered into with  True Consultants for the Soil Borings. This part of the project should start shortly.    Upcoming Road Work Update:   The sub-contractor working for Nardulli, began laying sod this week in the areas of Phase I.  Restorations may take until next week to complete.  All of the concrete work including spot curb removal and replacement, driveway aprons and structure adjustments are now complete on Beach.  Nardulli is starting on Oak today with spot curb and apron removals.  This work will last into late next week.  They will stay east of La Grange Raod until all concrete work is complete before jumping over the west side of La Grange Raod to begin the 600 block of Ashland and Oak between Ashland and La Grange Road.   Check back next week for another progress report.  

Facebook Twitter Email

Other News in Home

QPR2

Suicide Prevention Seminar

Posted on: September 5, 2019
brush

Brush Collection Schedule

Posted on: August 29, 2019
cannabis web

Recreational Cannabis Information

Posted on: August 12, 2019